Monday 21 September 2009

Belated progress pictures

One of the things I have been meaning to do since we've been back from France is to put up some more pictures of our progress over the summer but I have been distracted by work and other things and before I know it we are booking tickets for a return trip in October! However today we had an email from our neighbours telling us that they have had some heavy rain so had gone over to check our cellar and to see if the elaborate arrangement of pipes, drains and gravel had done the trick and cured the flooding problem.

Fingers crossed, it might have worked as the cellar and the sump were bone dry! Anyway, it prompted me to finish off this post.
Ian's first job was to run the pipes for one of the guest bathrooms. The pipes and wiring need to be in place before we can close the walls and the walls need to be closed before we can lay the heating pipes.

This proved a long and complex job. Ian is quite fussy about it all looking neat and as you can see from the charcoaled board, soldering the pipes in place was a challenge. Must remember to put a fire extinguisher in next trip! The trick now is to test the pipes to make sure they don't leak before we seal the wall. (We don't know yet how we will do this!)

The main achievement however was to do some of the groundwork. Up until now we have never had a proper entrance and the builder, perplexed by the flooding cellar, had merely left it un-rendered and with a great ditch in front of the front door. The way in was over a pile of old pallets which we referred to as our moat and drawbridge!



Well, with the help of Warren the moat has been filled and we have a proper path leading up to the front door!

No comments: